Third question. A statue was planned to be built by 40 people and completed in 15 days. If it were to be completed 3 days earlier, how/ many more pecple would you need?

Third question. A statue was planned to be built by 4040 people and completed in 1515 days. If it were to be completed 33 days earlier, how/ many more pecple would you need?

Full solution

Q. Third question. A statue was planned to be built by 4040 people and completed in 1515 days. If it were to be completed 33 days earlier, how/ many more pecple would you need?
  1. Calculate Total Work: Calculate the total amount of work required to build the statue in person-days.\newlineTotal work =Number of people×Number of days= \text{Number of people} \times \text{Number of days}\newlineTotal work =40 people×15 days= 40 \text{ people} \times 15 \text{ days}\newlineTotal work =600 person-days= 600 \text{ person-days}
  2. Calculate New Deadline: Calculate the new deadline for the project to be completed 33 days earlier.\newlineNew deadline == Original number of days - 33 days\newlineNew deadline == 1515 days - 33 days\newlineNew deadline == 1212 days
  3. Calculate Number of People: Calculate the number of people required to complete the work in the new deadline.\newlineNumber of people needed =Total workNew deadline= \frac{\text{Total work}}{\text{New deadline}}\newlineNumber of people needed =600 person-days12 days= \frac{600 \text{ person-days}}{12 \text{ days}}\newlineNumber of people needed =50 people= 50 \text{ people}
  4. Calculate Additional People: Calculate how many more people are needed in addition to the original 4040 people.\newlineAdditional people needed = New number of people - Original number of people\newlineAdditional people needed = 5050 people - 4040 people\newlineAdditional people needed = 1010 people